Anerobic Digestion Plant

Speyside, Scotland

Overview

JBD Tritec where contracted by Process engineering company who were responsible for the process plant package for the project, JBD had a previous working relationship with this company.


JBD Tritec are carried out mechanical Install of free issue equipment, installation of all Structural Steelwork, supply and installation of all pipework and installation of free issue pumps & ancillary equipment.

Project Specifics

  • Erection of 30no Free issue Vessels.
  • Erection of Free issue access platform for the tank farm.
  • Erection of Free issue Evaporator building, pipebridges and walkways.
  • Installation of Carbon Steel & Stainless Steel Pipework Ranging from DN15 to DN300.
  • Services included Process piping, Steam, Condensate & Gas.
  • Installation of plastic pipework & dual contained Hoses for Chemical Dosing systems.
  • Installation of pumps & ancillary equipment.
  • Project Duration 8 Months.