JBD Tritec were contracted by an individual distilling company on recommendation from a previous client.


JBD Tritec were the main Piping Contractor on this project, on this project all equipment was installed by the equipment supplier.

Project Specifics

  • Stress analysis design on new steam system.
  • All process and service pipework for the site.
  • Circa 2900m of pipework installed.
  • Installation of all ancillary equipment (pumps, heat exchangers, agitators etc).
  • On site commissioning assistance.
  • Project duration - 6 months.