Overview

JBD Tritec were contracted by an individual distilling company, working closely with the main design contractor.


JBD Tritec were the main mechanical contractor on this project.

Project Specifics

  • Installation of all free issue tanks and equipment
  • 3 copper stills
  • mash tun and equipment
  • 12 tanks
  • 10 washbacks
  • full boiler house and flue
  • 24 pumps & hexs
  • Stress analysis design and installation of new steam system.
  • All process  and service pipework for the site circa 2,800m.
  • Project duration - 9 months.

Gallery