Case Study
JBD Tritec were responsible for manufacturing and installing a new walk way system.
Services
- Pipework Engineering
- Mechanical Engineering
- Fabrication
- Pump Services
- Valve Services
- Heat Exchangers
- Conveyors
- Electrical Engineering
- Project Management
- Quality
- CDM, Health & Safety
- Case Studies
- Osprey Corporation – Scrubber Project at Strathclyde Distillery
- Powermaster – New Chiller Installation at Diageo Shieldhall
- Loch Lomond Distillers – Production capacity increase
- Project Tonic – Allied Distillers, Kennington
- Meat Processing Plant, Bridge of Allan
- Chivas Brothers – Relocation of equipment from Kilwinning
- Macfarlan Smith – Pharmaceutical works
- Whyte & Mackay – New access walkways for bottling plant, Grangemouth
- Krones UK – New distillery for William Grants at Girvan
- John Dewars – New bulk blends plant, Glasgow
- Pasteuriser Installation - Various Sites
- Scottish Sea Farms
- Scottish Water
- Corporate Video
JBD Tritec manufactured and installed a new walk way system
Loch Lomond Distillery
Client:
Loch Lomond Distillery
Client Challenge
Loch Lomond Distillery contracted Moulson Process Plant to design and build an extension to the distillery to deliver a 30 % capacity increase. JBD Tritec Ltd, as a key supplier over the years to Loch Lomond, were contracted to carry out the full mechanical installation. The range of services on offer were ideal for the works and with the consulting engineers based in Shropshire, they relied heavily on us to coordinate all activities.
JBD Tritec’s Solution
The project involved modifications to ten off second hand 200,000 litre vessels, erection of all tanks and supporting steelwork, this also involving coordination with Railtack as local rail services had to be accommodated.
Fabrication work further included design, fabrication and installation of a fifty metre long pipebridge / walkway, tank farm, stair towers and all associated walkways. We built pipebridge sections off-site complete with integrated pipework and later installed on site.
Pipework was also done for washbacks, pipebridge, cooling towers, wash charger and new still house extension in copper and stainless steel, including steam, condensate, air, etc. The project has run to everyones’ satisfaction and will be completed on time and on budget.